PLUTON took part in the InnoTrans 2024 in Berlin More details
Ukraine |en

2007-2010

Implementation of turn key projects. Supply of two traction substations for city electric transport, Kerch (Crimea). Installation, commissioning, startup.

PLUTON implemented the following modern equipment on substations:

  • KSO chamber 825 — 5 pcs.;
  • transformer TSZP — 3 pcs.;
  • rectifier series V-TPED — 3 pcs.;
  • switchgear series RU-600 — 12 pcs.;
  • auxiliaries cabinet — 2 pcs.;
  • operating current cabinet — 2 pcs.;
  • input unit — 2 pcs.;
  • combined protection cabinet — 1 pcs.