Kerch city electric transport
Kerch city electric transport was supplemented with 2 traction substations with modern new-generation equipment
2007-2010
Implementation of turn key projects. Supply of two traction substations for city electric transport, Kerch (Crimea). Installation, commissioning, startup.
PLUTON implemented the following modern equipment on substations:
- KSO chamber 825 — 5 pcs.;
- transformer TSZP — 3 pcs.;
- rectifier series V-TPED — 3 pcs.;
- switchgear series RU-600 — 12 pcs.;
- auxiliaries cabinet — 2 pcs.;
- operating current cabinet — 2 pcs.;
- input unit — 2 pcs.;
- combined protection cabinet — 1 pcs.