Sites

4 traction substations

Works performed

Turn-key project. Modernization of 4 traction substations for Beltsy city electric transport power supply network (the Republic of Moldova). Dismantling, installation works, commissioning, startup.

  • equipment for retrofit of existing switchgears 600 V — 33 sets;
  • rectifier — 12 units.

The Project was financed with the support of the European Bank for Reconstruction and Development (EBRD).